Seminole Blvd Sewer Improvements

The Seminole Boulevard / 8th Ave SW Sanitary Sewer Pipe Replacement Project will eliminate persistent sanitary sewer overflows along 1st Street SW and correct a number of aging infrastructure deficiencies along this one mile route. Read on for project updates, detours and more information.

DETOUR ROUTES
View Detour Routes

During Phases 1 and 2 of the project, students walking to Largo Middle School can expect all the sidewalk on the southside of 8th Ave SE/SW to be closed from 4th St SW to 2nd St SE. Pedestrians will need to use the north side and cross at 4th St SE or the Largo Middle school crosswalk.

CONSTRUCTION PHASES
Download the Full Phase Plans or view individual phases below. View the phases map.

PhasesMapPHASE 1:
  • Early-November 2020 to February 2021
  • Closure of 8th Ave SE between Seminole Blvd and 2nd Street SE
  • View Phase 1 Plan
PHASE 2:
  • March 2021 – June 2021
  • Closure of the eastbound lane of 8th Ave SW between 4th St SW and Seminole Blvd.
  • View Phase 2 Plan
PHASES 3-5
HAVE QUESTIONS?

For more information, please contact Brian Highnote, Project Manager, at 727-587-6713 x4402 or bhighnot@largo.com.