Community Development Department Project Status Matrix
|
Community Development Department Project Status Matrix
![]() | March 2013 Community Development Department Project Status Matrix PDF Matrix for Printing |
|
Project |
Project Location |
Application Date |
Land Use |
Acreage |
Description |
|
Chase West Bay |
801 West Bay Drive |
9/12/12 |
CRD-WBD |
3.64 |
Project is a 4,352 SF Chase Bank. A DRC was held on 9/25/12 and comments were sent to the applicant on 10/4/12. Revised elevations were received on 11/30/12. Commission approved to allow one story bank. |
| Clearwater Ice Arena | 13940 Icot Blvd | 1/31/13 | IL | 1.1 |
Project consists of a proposed 37,000 SF expansion to the existing ice rink facility. |
| Publix | 11992 and 12022 Indian Rocks Road | 12/2012 | CG | 11.25 | Redevelopment of a new 46,013 SF Publix grocery store. Plans routed to staff, comments due 3/20/13. |
| Neighborhood Walmart | Ulmerton Crossing 9020 Ulmerton Road | 11/16/12 | CG | 6.74 | New 118,000 retail store. Comments due to Applicant 12/14/12. Waiting on applicant for resubmission. |
| Walmart, Missouri | 990 Missouri Ave. | 2/01/12 | CG | 11.25 | Project consists of a proposed 118,000 SF large-scale retail store. Routed to staff 2/19/13. |
| Ulmerton Crossings Retail | Ulmerton/Starkey Road | CG | 2 | A 12,510 retail plaza. DRC meeting is scheduled for 3/13/13. |
| Approved Cases |
|
Project |
Project Location |
Application Date |
Land Use |
Acreage |
Description |
|
Barley Mow Brewing Company |
140t 6th St NW |
7/14/12 |
CRD-WBD |
.136 |
Conversion of an existing building to an office for the Barley Mow Brewing Company. A small scale review memo was signed on 8/14/12. |
| O'Reilly Auto Parts | 8551 Ulmerton Road | 09/26/11 | CG | 1.1 |
Construction of a 7,650 S.F. auto parts store. Project is pending, Development Order has been signed and a pre-construction meeting was held. Project under construction. |
| Buffalo Wild Wings | 10500 Ulmerton Road | 03/15/12 | CG | 33.5 | Project consists of a replacement of a 5951 SF restaurant. Project is completed. |
| St. Michael's Medical Center | 1018 West Bay Drive | 06/1/12 | CRD-WBD | 1.7 |
Construction
of a 21,320 SF Medical Office and associated parking. A neighborhood
compatibility meeting was held on 8/20/12. DO has been signed, pre-construction meeting held. |
|
Chase (Barclay Square) |
13883 Walsingham Rd. |
12/27/11 | CG |
0.74 |
Construction
of a new 4,450 S.F. Bank with three (3) drive thru lanes at Barclay
Square. Project is completed. |
|
Circle K |
1499 Belcher Rd. |
11/09/11 |
CG |
1.1 |
Demolition
of a vacant 3,016 S.F. bank to redevelop the site with a 4,000 S.F.
building consisting of a gas station and convenience store. Project is complete. |
| Thornton's | 8875 Ulmerton Rd | 02/29/12 | CG | 1.45 |
Project
may consist of a 3,000-4,000 SF gas station and convenience
store. Project is under construction with an estimated completion date of December 2012. |
|
Clear Channel Outdoor |
55555 Ulmerton Rd. |
10/06/11 |
IL |
9.27 |
A portion of the property will be redeveloped to accommodate a new 8,930 S.F. corporate office building with the eventual demolition of the existing 6,191 S.F. office building, while maintaining all other commercial buildings on site. New Office building is complete. |
|
Seasons of Largo |
4175 East Bay Dr. |
11/30/11 |
CG |
2. |
A Class 2 Use Development to allow for the replacement of the existing three-story, 54,492 square foot office building to a one-story, 42,500 square foot building for an 80 bed assisted living facility. Project is under construction with estimated completion date of Second Quarter 2013. |
|
Highland Office Building |
400 Highland Ave. |
07/29/11 |
REC/OS |
36.16 |
14,601 SF professional office building. Project is pending and a Development Order has been issued. |
|
Highland Recreation Complex |
400 Highland Ave. |
07/29/11 |
REC/OS |
36.16 |
Construction of a new 45,695 S.F. recreational complex. Project under construction with an estimated completion of 4/2013. |
| Largo Skate Park | 375 Seminole Blvd. | 09/12/12 | CRD-WBD | 3.84 | New skate park at
Bayhead Sports Complex. Small scale signed, and project estimated completion is 4/2013. |
|
McDonald's (Crossroads) |
2675 Roosevelt Blvd. |
12/28/11 |
CG |
1.21 |
Construction
of a new 3,889 S.F. restaurant. Project is completed. |
|
McDonald's |
1250 West Bay Dr. |
01/30/12 |
WBD-CRD |
1.36 |
New
4,365 Square Foot building, reconstruct/improve the existing parking
area, provide new landscaping, provide new signage, improve the
drainage system and provide other improvements to the property as
required by the Comprehensive Development Code.Project is completed. |
|
Metro Storage |
13100 66th St. |
12/30/99 |
CG |
8.19 |
Renovations to existing self storage building and site improvements. A small scale memo was approved and signed. |
|
Pinellas County Sheriff's Complex |
10750 Ulmerton Road |
06/24/11 |
I |
41.7 |
New
construction of a new Sheriff's Administration Building, Emergency
Operations Center, parking garage, vehicle maintenance building, and
central energy plant. Under construction with estimated completion date Second Quarter 2013. |
|
Pinellas Heights |
11411 Ulmerton Road |
02/07/12 |
CG |
38.17 |
Construction
of a 153 Unit apartment complex. A Development Agreement was
completed and recorded in Pinellas County on July 20, 2012. Demolition of existing structure complete. |
| Whitney 19 Self Storage | 16809 US 19 | 10/11/12 | CG | 5.444 | Construction of 5,750 square foot storage building. |
| Rubin Professional Offices | 58th St. North & Ulmerton Rd. | 08/19/11 | IL | 2.17 | Professional office building. Planning is awaiting a slight revision and the Development order was signed. Under construction. |
| Seasons of Belleair | N1704 Clearwater-Largo Rd. | 11/30/11 | CLR-CRD | 6.31 | Project consists of an 80-bed Assisted Living Facility. Under construction. |